Project Itinerary
Thu-11-Sep:
Set moorings; Place baseline for reference; Check/replace reference
lines from moorings; Re-label/replace artifact tags; Tag/label baseline
stakes; Place transect line endpoints; Dust off/cleanup any recent sedimentation
of south exposure; Pour footings for photo-grid verticals
Fri-12-Sep:
Finish incomplete Thu tasks; Assemble photo-grid on Shellpoint; Test
computer hardware/software setup on Shellpoint
Mon-15-Sep:
Orientation dive for divers onsite; Shoot test photos and video for
visibility-elevation-spacing; Set photo-grid as necessary on first location
(100,70-90); Shoot digital stills
Tue-16-Sep/Wed-17-Sep/Thu-18-Sep:
Shoot and move with photo-grid until exposed areas are covered; As the
last digital still work is being completed, place transect lines for
digital video; Scoot and shoot N-S video lanes, starting from the east
side of site and moving west; Locate and run line/tape(s) from south
baseline (100,0) to south anchor; Shoot out and back video to moorings,
screw-eye, and south anchor to tie into overall mosaic
Fri-19-Sep:
Finish incomplete target tasks; Clean-up and secure site for winter
inspection dives
Peripheral Tasks as time permits:
Baseline stake elevations; Control-point elevations; Triangulation of
screw-eyes and moorings to baseline;
Divers:
Digital Still (2-4):
1 Photographer and 1+ Assistants (if necessary) for shooting; 4 divers
for moving photo-grid
Digital Video (4):
1 Videographer and 1 DPV Pilot; 2 divers for line tending/moving
Elevations/Triangulations (2+):
Buddy teams as assigned
|