By next week test units should reach the southernmost
cannon, one of fourcontained in the planned excavation area and designated
for retrieval. Check back for the next update from the field.
Entry 09- 13 October
2006 Expedition Log
Chris Southerly, QAR Archaeological Supervisor
Monday
Tuesday
Wednesday
Thursday
Monday 9 October

Marginal weather from the weekend lingered into Monday morning so the
crew took advantage of the poor conditions to do some shore work. Recently
constructed artifact tanks were picked up from Parker
Marine Enterprises where they were being coated and transported
to the conservation lab in Greenville. Minor maintenance was done on
Shell Point's pump, dive gear, and the
sluice-screen system.
Supervisors also caught up on paperwork and other project details.
Tuesday 10 October
Winds were still strong out of the north but conditions at the site
were relatively calm despite poor visibility.
Archaeologists
completed units 47 and 48 along the east side of the site before setting
up and beginning excavation on units 49, 50, and 51 further east and
north to define the eastern site boundary. Work continued in the south
units 43, 44, and 45 with the 3" sluice-screen system. Lead patching
was recovered along with lead shot both on the bottom by divers and
in the sluice-screen recovery system on the surface.
Wednesday 11 October
Sea conditions
were remarkably calm allowing work to continue in units 43 and 44 with
the sluice-screen system,
while
archaeologists completed units 49, 50, and 51 along the eastern site boundary.
Researchers began excavation on units 52, 53, and 54 across the reference
baseline, working west and south from the eastern boundary units. Unit
55 was also excavated in the south to better define the southern site
boundary.
The
artifact highlight of the day was when large quantities of small lead
shot as well as gold flakes and dust started being recovered in the
sluice-screen from unit 43. Lead patching and iron concretions were
also mapped and recovered from units 43 and 44. Larger diameter lead
shot also began showing up in unit 52 further east and ceramics in unit
53.
Work continued late into the day with the prospects of marginal weather
on Thursday.
Thursday 12 October
Strong southwest winds did not bode well for site conditions and after
heading out to check the wind and seas proved too rough for safe operations.
Taking advantage of another weather day project staff continued to pan
sediments collected from the sluice-screen recovering additional gold
and small lead shot. Additional dive equipment repairs were made while
planning for the surface-supply/hookah system being added next week.
The surface-supply system will allow excavation divers and documentation
divers to extend their bottom time while reducing the number of daily
SCUBA cylinder fills. Construction also began on a custom tank to accommodate
the sternpost first discovered in May 2005. Archaeologists are examining
the possibility of only recovering one or two cannon this fall rather
than the planned four, in favor of recovering the sternpost.
Supervisors continued working on paperwork and documentation checking
completeness and accuracy. Good documentation of not only what is being
found but where is it coming from on the site is essential. Archaeological
excavation to uncover, document, and recover artifacts destroys its
site context forever. Artifacts can never be put back, so one of the
key elements of archaeology is to preserve/record the relationship between
the artifacts and with their environment with the least possible disturbance.
Every effort is made to record all features and relationships before
they are lost by removal.
Entry 16-20 October
2006 Expedition Log
Chris Southerly, QAR Archaeological Supervisor
Monday
Tuesday
Wednesday
Thursday
Friday
Monday 16
October


Long time Underwater Archaeology Branch volunteer Jim Dugan and Florida
state underwater archaeologist Roger Smith joined the team for this
week. Excavation, documentation and recovery of artifacts continue on
units 52, 53, 54, 57, 58, 59, 60, and 61.
Tuesday 17 October

Overcast with light winds today but good working conditions. On the
way out Shell Point attaches to the warning buoy, which had gradually
moved inshore from recent storms, and reposition it back at the site.
On site, archaeologists continue on open units.
Wednesday 18 October

Poor weather conditions delay departure so the crew shares a large
team breakfast at the Ft. Macon barracks waiting for the winds to die
down. Work continues on open units, recovering more lead shot and gold
from the sluice/screen. The weather picks up again in the afternoon
cutting the workday short.
Thursday 19 October

Light variable winds today make up for the lost time earlier in the
week. Units 64-70 are completed and archaeologists set up units 71-74
to the southern side of the planned excavation area and units 75-77
to the northern side of the excavations.
Friday 20 October

Weather again prevents fieldwork so most of the crew takes the option
for a three day weekend. Excavations next week should begin uncovering
the first of the cannons within the planned recovery area. New units
will also be moving into the area where two intact glass onion bottles,
as well as brass artifacts and scientific instruments were recovered
during the 1998 exploration trench. More to come....
Entry 23-27 October 2006 Expedition
Log
Chris Southerly, QAR Archaeological Supervisor
Monday
Tuesday
Wednesday
Thursday
Friday
Monday 23 October

Weather did not look promising as the crew was heading out. Winds were
north-northwest 15-20 knots. Visibility on the bottom was very good,
10+ feet. By mid-day the winds died down and work progressed will with
improved visibility. Units 71, 72, 73, and 80
were completed while overburden was removed from units 75, 76, and 77.
Cannon C16 is beginning to be exposed by the excavations in 75 and 76.
Original plans for the fall field season included the recovery of as
many as four cannon from the site (C12, C16, C17, C18). Expansion of
the excavation area east to west and the logistic difficulty of arranging
a lifting/recovery vessel will likely result in delaying cannon recovery
until the spring expedition.
Tuesday 24 October

Winds were too strong to go out today so the crew worked onshore. Part
of the crew panned sediments collected from the sluice/screen, recovering
more gold and small lead shot. Others worked on the final testing of
the surface-supply diving system for use with the teams AGA full-face
dive masks (Ocean Technology Systems Divator Mk II).
Wednesday 25 October

Clear and cold with winds light and variable, primarily from the northwest,
allows work again on site. Visibility was excellent varying between
10 and 15 feet all day. Units 77, 78, and 79 were completed and unit
81 was finished other than final cleanup.
Thursday 26 October

Clear and cool again, winds from the northwest. Researchers finish
final cleanup and sand sampling of unit 81 and complete three additional
recovery units (82, 83, and 84). Testing was done of a 6" sluicing
system to compliment work being done with the 3" system. The 6"
sluice was moderately successful collecting an excess of sterile sediment
while being difficult to maneuver and handle on the bottom around artifacts.
Researchers decided do discontinue use of the 6" and rely on the
3" sluice system for careful excavation and recovery.
Friday 27 October

The marine forecast is marginal but the crew decides to try to get
as much work done before the weather conditions turn. Units 85 and 86
are completed before the swells increase to make work too difficult.
The crew cleans up and secures the site for the predicted weekend gale.
Researchers anticipate much of the coming Monday will be spent cleaning
up the site and removing slumping sand from excavation areas.
Entry October 30-November 3 2006
Expedition Log
Chris Southerly, QAR Archaeological Supervisor
Monday
Tuesday
Wednesday
Thursday
Friday
Monday 30 October
As anticipated the strong winds and waves from the weekend gale affected
the site. The excavation unit grids were all buried from slumping sand
and much of the morning was spent uncovering them and getting back the
previous depth of excavation. The main baseline and the reference lines
from the east mooring and west mooring were also broken. Reconnaissance
dives also revealed extreme scour to the west and south of the main
ballast pile. Ballast, concretions, and cannon were all exposed to a
depth previously unobserved.
One team worked re-establishing lines and resetting excavation units,
while another began documenting new areas of exposure. Near the end
of the day researchers were back to previous levels and could resume
working on unit 87.
Tuesday 31 October
Very
light wind from the south gave the team calm seas but poor visibility
dominated the day as low tide was early in the morning. Work continued
completing units 87 and 88. Extensive artifacts as well as lead shot
and gold flakes/dust came from unit 88. Researchers worked on unit 75
containing much of cannon C16 mapping and recovering artifacts and lead
shot.
Exposure recon recovers two large earthenware fragments, another piece
of glazed ceramic, and shows hull structure (pine sacrificial planking)
extending at least as far south as cannon C1. Estimates are that the
normally exposed area of the site has doubled with the recent scour.
Wednesday 01 November

Weather was sunny with light winds from the south with moderate swells.
Visibility on site was only 2-3 feet with a moderate surge. Site cleanup
and repair continues today, checking moorings and other lines. Work
is finished in unit 75, leaving only cannon C16. Excavation in unit
76 showed multiple concretions and layers of lead shot, especially under
concretions.
Divers had a disagreement with the site's resident octopus this morning.
Overnight he had taken up residence in the intake hose of the 6"
dredge. It took quite some time to convince him that being in the intake
when the suction started was not a good idea. He eventually moved without
injury or inking to the octopus or the divers. Once the octopus moved
to under the lead sheet attached to cannon C16 divers used the 6"
dredge to uncover the 5'x15' reference grid and move it to its new location
on units 14, 91, and 92.
Thursday 02 November
Wind
light and variable, mostly from the north. The 10'x10' reference grid
is repositioned over units 8, 93, 94, and 95. One team works using surface-supply,
mapping newly exposed area of the site. The second team works on excavation,
documentation and recovery, completing units 93 and 94. A complete cluster
of cask hoop concretions was recovered from 94/8 along with numerous
other smaller concretions. The greatest quantity of lead shot yet is
recovered from units 93 and 94. The recovery sluice had to be stopped
several times during the excavation process as it was completely full
of lead shot.
Friday 03 November
Strong
winds from the north and cold temperatures convince the crew to call
another shore day. The large quantity of concretions and artifacts recovered
during the week are packed and loaded for transport to the conservation
lab in Greenville. Other crew members pan the sediments from the week's
sluicing for additional lead shot and gold. Others work on equipment
cleaning and maintenance and getting the teams second 3" dredge/sluice
system configured.
Afternoon conditions improve as the winds die down and everyone is
optimistic for good weather for the final week of the project. With
70 units completed the team has already exceeded the fall project goal
and with the exception of cannon recovery we may still reach the 50'
baseline goal.
Entry 06 - 08 November
2006 Expedition Log
Chris Southerly, QAR Archaeological Supervisor
Monday
Tuesday
Wednesday
Monday 6 November
Weather
today is cooler with moderate winds out of the north-northeast. While
not ideal, the conditions are certainly workable. With the forecast
for the remainder of the week not promising work focuses on cleaning
the lead shot left in unit 8 after the May
2005 expedition, and completing unit 92. As the day progresses winds
pick up from the northeast making the seas choppy and causing a moderate
surge to build on the bottom.
As it always seems, we inadvertently save the best until last. Excavation
in unit 92 exposes quite a bit of material. First and foremost is the
discovery of a bell incorporated in a larger concretion. This is the
second bell located on the site and although small (approximately 8.5
inches in diameter) appears to be more of the type to have been a ships
bell. Along with the bell a nearly intact crank jack, similar to one
recovered previously from the site, as well as a lead cannon apron.
Numerous smaller concretions also come from the unit including a buckle
identified on the bottom.
While all the excitement of new discovery is happening, we have five
visiting divers taking a tour of the site from NC Marine Fisheries examining
the exposed remains from the perspective of a near shore artificial
reef.
Tuesday 7 November
The crew is on site by 7:45 and divers begin setting up for unit 91.
By 8:15 the winds are already beginning to turn to the south. With the
swells building and the marine forecast for the next few days very marginal
for work the decision is made to begin cleaning up the site rather than
starting a final unit. One team begins recovering mapping frames, reference
lines, and securing/removing moorings, while a second team finishes
mapping in and recovering potentially endangered isolated finds from
newly exposed areas of the site near the main pile.
The crew returns to dock by midday and offloads and stows the gear
from R/V Shell Point. Once unloaded, one team heads back out hoping
to be able to detach and bring the warning buoy in for maintenance before
the coming storm. Conditions prove too rough already to safely retrieve
the buoy and fieldwork for the fall expedition officially comes to a
close.
Wednesday 8 November

Strong winds and heavy rains overnight have passed by morning with
only a lingering breeze. The crew spends the morning cleaning gear,
and packing and stowing equipment for transport and storage. The final
field processing of artifacts takes place as they are checked, loaded,
and secured for the trip to the lab in Greenville. Everything is complete
by early afternoon and the Fall 2006 field crew breaks for the final
time to go their various directions.
With over 25-percent more area covered than planned, excavation-documentation-recovery
methodology refined, new equipment tested, and many potentially significant
artifacts discovered the Fall 2006 Field Expedition was without a doubt
an outstanding success. Stay tuned as more information becomes available
about newly recovered artifacts as they are processed and examined at
the conservation lab.